Tenant Operations

East Hollywood — 30 Bays — Bay-level status, onboarding pipeline, and revenue impact

Occupied Bays

10 / 30

Occupancy

33%

Below target

Revenue Potential

$198K/mo

Revenue Actual

$66K/mo

33% of potential

Avg Days to Operational

47d

Active Onboardings

3

Bay Grid

Construction
Ready
Onboarding
Occupied
Turnover
Maintenance

Onboarding Pipeline

3 Active
OperatorBayCurrent StageDays at StageTarget DateBlocker
Green Bowl#11Appliances Installed5dMar 15, 2025
Falafel House#12Plan Approved12dMar 24, 2025Equipment vendor backordered 2 weeks
Ramen Lab#13Rep Assigned4dApr 12, 2025Bay data drop not installed yet

Turnover Tracker

2 Active
BayOutgoingIncomingDays VacantRevenue LostModificationCondition
#29Burger JointVacant14d$3,080None8.5/10
#30Pasta PalacePending15d$3,300$4,2006.2/10

Revenue Delayed

$155,100

Total revenue impact from delays & gaps

construction delay$92,400
permit delay$52,800
inspection failure$4,400
turnover gap$3,300
onboarding delay$2,200

Impact Events

construction delay-$92,400

Electrical panel upgrade delayed by LADWP — 2-week wait for 2000A service

14d delayed30 baysBy: utility
permit delay-$52,800

Fire sprinkler plan rejected — LAFD required additional calculations

8d delayed30 baysBy: permitPreventable
onboarding delay-$2,200

Health inspection failed — grease trap size insufficient for Bay 12 cuisine type

10d delayed1 bayBy: constructionPreventable
turnover gap-$3,300

Bay 30 required floor drain modification between tenants

15d delayed1 bayBy: constructionPreventable
inspection failure-$4,400

Ansul system failed acceptance test — incorrect nozzle placement

5d delayed4 baysBy: subPreventable