VALENCE Cost Forensics

Pay application audit & anti-fraud detection

Change Orders

Scheduled Value

$1.8M

GC Billed

$546K

PM Verified

$446K

Variance

$100K

18.3% of billed

Lines Flagged

6/10

#DescriptionTradeScheduledGC %GC BilledPM %PM VerifiedVarianceFlag
1General Conditionsgeneral$210,00055%$115,50052%$109,200+$6,300OK
2Demolition & Site Prepgeneral$145,0000%$00%$0$0OK
3Concrete & Masonrygeneral$180,00025%$45,00020%$36,000+$9,000flag
AI Flag: GC claims 95% complete but typical progress at this stage is 90%. Variance: $9,000 (5% of scheduled)
4HVAC — Ductwork & Equipmentmechanical$320,00040%$128,00030%$96,000+$32,000critical
AI Flag: OVERBILLING: GC claims 70% complete but ductwork installation is only 60% per site observation. $32K variance = 10% of scheduled value.
5Electrical — Rough-inelectrical$195,00035%$68,25033%$64,350+$3,900OK
6Plumbing — Rough-inplumbing$165,00030%$49,50028%$46,200+$3,300OK
7Fire Protection Systemfire$125,00050%$62,50030%$37,500+$25,000critical
AI Flag: OVERBILLING: GC claims 70% but Ansul system not yet installed. Only rough piping complete (30%). $25K variance = 20% of scheduled.
8Grease Interceptorplumbing$42,00085%$35,70080%$33,600+$2,100warning
AI Flag: Price: $42K for interceptor implies $2.80/SF — benchmark is $1.47/SF. Possible price inflation.
9Interior Finishesfinishes$98,00015%$14,70010%$9,800+$4,900flag
AI Flag: GC billing 15% on finishes but framing not complete. Premature billing.
10Equipment Installationmechanical$270,00010%$27,0005%$13,500+$13,500flag
AI Flag: GC billing for stored materials. Equipment on-site but not installed. PM verified 5% for receiving only.
TOTALS$1,750,000$546,150$446,150+$100,0006 flags

Cost vs Portfolio Benchmark ($/SF)

General Conditions$14.00 vs $14.00/SF
Concrete & Masonry$12.00 vs $12.00/SF
HVAC — Ductwork & Equipment$21.33 vs $21.33/SF
Electrical — Rough-in$13.00 vs $13.00/SF
Plumbing — Rough-in$11.00 vs $11.00/SF
Fire Protection System$8.33 vs $8.33/SF
Grease Interceptor$2.80 vs $2.80/SF
Interior Finishes$6.53 vs $6.53/SF
Equipment Installation$18.00 vs $18.00/SF