CK Dallas Deep Ellum
CK Dallas Deep Ellum · Texas Build Group · PM: David Phung
Contract Value
$1,750,000
Total Budget
$2,300,000
Permits
1
Change Orders
2
Permits (1)
buildingHouston Permitting
approvedInspections (2)
Managebuilding rough2024-05-20
scheduledplumbing rough2024-05-25
failChange Orders (2)
| CO # | Description | GC Amount | Ind. Est. | Flag | Status |
|---|---|---|---|---|---|
| 1 | Relocate grease interceptor from interior to exterior | $67,000 | $38,000 | critical | under review |
| 2 | Additional electrical circuits for 4 new prep stations | $18,500 | $16,000 | warning | submitted |