Midwest Commercial Builders

FLAG

ATM Chicago Buildout · License: IL-GC-44821 · 8 prior ATM projects

$2,180,000

$145.33/SF · 22 weeks

VALENCE Score

45/100

Fraud Risk

HIGH

Flags Detected

4

2 critical

Savings Potential

$355K

Historical CO Rate

9.2%

Above 3% target

Bid vs Market Benchmark ($/SF)

Market Benchmark Within Range Elevated Flagged
Line ItemMaterialLaborEquipTotal$/SFMarketVarFlag
General Conditions$0$145K$0$145K$9.67$7.00+38.1%
Demolition & Site Prep$15K$95K$35K$160K$10.63$9.50+11.9%
Concrete & Masonry$85K$75K$20K$198K$13.20$12.00+10.0%
HVAC Ductwork & Equipment$145K$125K$55K$364K$24.27$21.33+13.8%
Electrical Rough-in$65K$110K$20K$215K$14.30$13.00+10.0%
Plumbing Rough-in$55K$85K$25K$182K$12.10$11.00+10.0%
Fire Protection$45K$65K$15K$140K$9.33$8.33+12.0%
TOTAL$410K$700K$170K$2,180,000$145.33/SF

Cost Composition by Trade

TK 7 Mechanisms Score

M1: OWN the Real Estate8.0

Ownership position secured

M2: VERIFY Every Dollar7.0

General Conditions: 38.1% above market

M3: STANDARDIZE the Design5.0

General conditions $9.67/SF — possible staff padding

M4: PROCURE at Volume10.0

Material pricing within volume benchmark range

M5: War Room COORDINATE4.0

Schedule 22 weeks exceeds ATM standard 18-week template

M6: AUTOMATE with LATTICE7.0

VALENCE analyzed 7 line items against 10 benchmarks

M7: ROBOTICIZE Over Time5.0

Pre-fab MEP racks: implemented

Fraud Flags (4)

General Conditions: 38.1% above market

Bid: $9.67/SF vs Market: $7.00/SF

M2 · pricingSave $40K

Request itemized breakdown. Compare to portfolio benchmark of $7/SF.

GC historical CO rate: 9.2% (target: <3%)

Midwest Commercial Builders has averaged 9.2% change orders across 8 ATM projects

M2 · historySave $135K

Require fixed-price contract with liquidated damages for CO rate >3%. Consider alternative GC.

General conditions $9.67/SF — possible staff padding

ATM template allows $7.00/SF for standardized 30-bay buildout. This bid is 38% over.

M3 · laborSave $40K

Request superintendent schedule. ATM standard template requires 1 super + 1 PE, not 2 supers.

Schedule 22 weeks exceeds ATM standard 18-week template

4 extra weeks = $140,000 in lost revenue

M5 · scopeSave $140K

War Room coordination should compress to 18 weeks. Require phased milestone schedule.